Senior Planner, Contrack International Inc, FY07 SOF Aircraft Operations, SIDRA Medical & Research Centre and Science & Technology Park

START Date: 
April, 2007
END Date: 
July, 2011

Involved in the construction of a Rotary and Fixed Wing Aircraft Hangar, Squadron Operations Facility, Aircraft Washrack, Fuel Stand Sunshade, Pump Building, Substation Building, Fire Pump Building, Access Apron, Site Supporting infrastructure and utilities at Al Udeid Air Base, Qatar.

Sidra is a World-Class Hospital is rising at Qatar and provides an environment to attract the best healthcare talent in the world. This project is about 200,000 SQM as a Design & Build Package is to be executed with JV of Contrack (Orascom)and Spanish OHL limited.

The scope of project comprises of finishing work over the main skeleton (Steel structure) of three unique buildings to commissioning & handover to end user (EADS, EXXON MOBILE, SHELL, and TOTAL & MICROSOFT). This package includes massive MEP work & state of the art architectural finishes. Budgeted with a 13 million man-hours.

Experience Hours (Planning & Scheduling): 
6200
Experience Hours (Cost Management): 
3100
Experience Hours (Forensic Analysis): 
1100