Schedule Control Engineer, JGC - Japan Gas Corporation, Multi-Project

START Date: 
August, 2006
END Date: 
June, 2007

Current Role Position: Planner/Scheduler – Control and Technical Section

 

§  Update construction master schedule in Primavera Project Planner (P3) based on subcontractor’s weekly progress submittal.

§  Monitor and update manpower allocation and mobilization plan as per JGC standards.

§  Monitor and Evaluate subcontractor’s progress based on man-hours, budget quantity and work productivity as per JGC’s standards.

§  Monitor and highlight construction schedule milestones in the construction master schedule and evaluate based on the planned and forecasted schedules.

§  Produce weekly and monthly progress report for the Construction Manager.

§  Create and establish crane lifting study Monitor and control construction master schedule as per Functional Work Breakdown Structure (FWBS) based on material shipment, man-hours, budget quantity (BQ) and work productivity.

§  plan using 4D CAD schedule simulation tools.

§  Establish the 3D model of construction equipments, facilities and other structures used for schedule simulation of the project using Microstation.