OnSite Senior Planner, Granite Services International Incorporation Sub GE, Several Power Plants in Iraq, UAE and Morocco

START Date: 
December, 2004
END Date: 
September, 2009

SeniorSite Planner / Site Lead planner / Cost Controls for General Electric’s Power Plants Projects in Africa and Middle East

Master schedules Level 1 to 5 in Primavera P3 and MS Project, WBS, critical paths analysis, payment/progress and performance measurements, analysis of historical data and variances, review of trend indicators, alternatives for recovery plans and corrective actions with stakeholders, monthly, weekly and daily reporting of project data in an accurate and timely manner for the following projects :

300MW Centrale Turbine a Gaz de Mohammedia 3 x 9E   for “Office National de l’Electricité” (ONE) in Morocco.

660MW Al Zawra Power Plant for Federal Electricity & Water Authority (FEWA) in the United Arab Emirates.

440MW Hamriyah Power Plant, Gas Plant, & 2*10MW Emergency Diesel Generators Plant (Wartzila) for Sharjah Electricity & Water Authority (SEWA) in the United Arab Emirates

220MW Baghdad-South Power Plant, Fuel Oil treatment plant, Water Treatment plant & storage tanks for BECHTEL as part of IRAQ’s reconstruction plan