Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

PLANNING & SCHEDULING ENGINEER - FIELD MANAGER, PT. INTI KARYA PERSADA TEHNIK, BOILER, Petrochemical

START Date: 
June, 1996
END Date: 
March, 2012

Major Project Experience (17 years experience)

  • Coal Boiler Project & Ammonia Urea (Pupuk Kaltim, Indonesia), Sep 2011 - Now
  • Ammonia ura Collie Phase1 – Project Development Phase (Perdaman Chemicals & Fertilizers Pty. Ltd, Perth, West Australia), Sep.2009 – Jan. 2011
  • Qatar 3LLNG (QGX, RGX, QCS), Rass Laffan – QPG, and AKG2 LNG (Chiyoda Corp, Yokohama, Japan), Mar 2007 – Mar 2008
  • South Sumatera Gas Development (Pertamina EP, Indonesia), June 2004 – Nov. 2006
  • Ammonia Urea Kujang-1B (Pupuk Kujang, Indonesia), Mar 2004 – May 2004
  • Malaysia MLMG 3 (M.W. Kellogg, Bintulu, Serawak, Malaysia), March 2003
  • Central Gathering Station 10 (Caltex Pacific Indonesia, Indonesia), April 1999 – Oct. 2001
  • Bontang LNG Expansion Train-H (Badak LNG, Indonesia), Jun. 1996 –  April 1997

 

Detailed Experience

Career highlights,       

 

June 1996 – Feb. 2012 PT. INTI KARYA PERSADA TEHNIK

 

RISK MANAGEMENT OFFICER                               Jan.2011 – Feb.2012

 

Coordinate project risk identification, selection, assessment, and mitigation plan among functions.

 

 

OWNER PROJECT PLANNER                                 Sep.2009– Jan. 2011

 

COLLIE UREA PROJECT PHASE #1 – PROJECT DEVELOPMENT AGREEMENT PHASE(PERDAMAN CHEMICALS & FERTILIZERS Pty. Ltd, PERTH, WEST AUSTRALIA)

 

Main responsibility; develop and track Owner Schedule of Financial Close milestone, check and review EPC Contractor (Samsung)’s PDA Schedule & EPC Schedule. Other responsibilities include prepare Owner engineers manpower planning, prepare notes of meeting, involved in the weekly review meeting.

 

** Diverse of Nationality Environment : Australia, America, New Zealand, India, South Africa, South Korea

 

PROJECT CONTROL MANAGEMENT TEAM           Apr.2008 – Sep.2009

PROJECT CONTROL MULTITASKING:

 

Supervise, guide, and analyze the on-going Projects in corresponding to the schedule and progress maintenance for the following projects:

 

1.     EPC Gas Station; Singa Gas Development (SGA) Project, Sumatera Selatan. PT Medco Energy (2008-2009).

2.     EPC Storage Depot; Terminal Transit Utama (TTU) Tuban, Tuban Jawa Timur. PT Pertamina (2007-2009).

3.     EPC ROPP (RCC Off-Gas to Propylene Project) Balongan, Indramayu. PT Pertamina (2008-2009).

4.     EPC MNK Project, Cikampek, Jawabarat. PT MNK (2009-2011)

5.     FEED Timika Cement Plant Project, Timika, Papua. PT Freeport & Local Government. (2009).

 

Project Control Coordinator and/or planning advisor for the following proposals:

 

1.     Project Management, Engineering, & Construction Services (PMECS); PT Chevron Pacific Indonesia (2009)

 

** Diverse of Nationality Environment : British, India, America

 

2.     AN/NA Kaltim Nitrate Indonesia (KNI) Bontang Plant, Kalimatan. PT Kaltim Prana Industry.

 

Acting as Planning & Scheduling Home Office Dept. Head for Home Office System Development, i.e.:

 

1.     Develop IPCS (Integrated Project Control System)

2.     Develop and Update Departmental Procedures

 

 

LNG PROJECTS EXPERIENCES

 

SENIOR SCHEDULER & COST COORDINATOR      Mar2007– Mar 2008

 

QATAR 3LLNG (QGX, RGX, QCS), RASS LAFFAN – QPG, and AKG2 LNG PROJECT (CHIYODA CORP., YOKOHAMA, JAPAN)

 

Assigned in Scheduling Group of Construction Division – Shinkoyasu Office, Yokohama – Japan. The main tasks and responsibilities are to evaluate Level-4 Subcontractor’s schedule and resource plan, analyse commodity work load, check the piping area density, and check the work critical path. Primavera v 3.1 is mainly utilized in this almost daily tasks.

 

 

NSB – NIGERIA NLNG, AMG2 – SAUDI ARABIA (CHIYODA CORP., YOKOHAMA, JAPAN)

 

Develop Level-2 EPC schedule using Primavera PM v 5.0

 

 

LNG STANDARD NETWROK FOR 78,000,000 TON BASE (CHIYODA CORP., YOKOHAMA, JAPAN)

 

Develop standard LNG network schedule to be stored as in-house template in the Methodolgy Management of Primavera v 5.0.

 

** Diverse of Nationality Environment : Japan, Philippine, India

 

 

FIELD SCHEDULER                                                March 2003

 

MALAYSIA MLMG(M.W. KELLOGG, BINTULU, SERAWAK - MALAYSIA)

 

The main tasks is to support M.W. Kellogg Field Project Control schedulers during Pre-Mechanical Completion activities to make ready the systems for Start-Up.

 

** Diverse of Nationality Environment : Malaysia, Philippine, Japan, America, India

 

 

 

 

SITE PROJECT CONTROL MANAGER                   June 2004 – Present

 

PROYEK PENGEMBANGAN GAS SUMBAGSEL PAKET-II & PAKET-III - PT. PERTAMINA EP (MUSI – PAGARDEWA - MERBAU, SUMATERA SELATAN)

 

It was a multi-area Gas Project that consists of a 175 KM Pipeline from Musi Barat to Pagardewa, Compression Station Benuang, Gathering Station Merbau, Gas Custody Station Pagardewa, and SCADA System.

 

The general responsibility is to control overall tasks in order to maintain Project Milestones through good preparation, accurate planning, intensive monitoring, comprehensive evaluation, and corrective action. Especially, he was responsible to control progress of time and costs of the construction works and measure indications of the project healthy by developing effective site project reports that express current works performance and the overlook. He monitored all lines of the Project Control tasks in order to maintain subcontractor’s performance, critical drawings availability, engineered material & equipment readiness on-site, progress trends, schedule critical paths, cost & expenses, and regular reports. Conducting inter-department interface and information / data exchange through intensive discussion, meeting and reporting. Communicating and co-ordinating with Home Office Project Control Team for the Construction Status in relation with Engineering and Procurement Status. Other responsibilities are to control project changes and to prepare project close out.

 

 

3D MODEL & SCHEDULE INTEGRATION               June – June 2004

 

SMART PLANT REVIEW INTERGRAPH, KUALA LUMPUR MALAYSIA.

 

Integrating P3 Schedule with 3D Model Smart Plant Review.

 

                              SCHEDULE ADVISOR                                                         Mar 2004 – May 2004

                             

                              PROYEK KIJANG-1B OSBL, PT. PUPUK KUJANG (CIKAMPEK, JAWA BARAT).

 

·       Responsible to make any schedule advices, identifying critical area, and finding solving problem. Making schedule risk thresholds in order to get earlier warnings of the some critical conditions that were happening on site construction. Confirming to all related disciplines that everything is alright regarding readiness of all resources (subcontractors, drawings, supervisors, safety, and so on) that are needed to fulfil achievement of CRD (Construction Required Dates). He, by spot checks, made sure directly to the originators any information that was felt unclear. He frequently focused and encouraged Disciplines to push up their progress trend and to avoid delay. He arranged team solutions by involving subcontractors to mitigate impact if the work progress delayed can not be avoided. Advising Site and Project Management of the any foreseen critical project situation and to get their required decision to overcome the obstacles and constraints.

 

PROPOSAL SCHEDULE COORDINATOR                            July 2003– Mar 2004

 

PROYEK PENGEMBANGAN GAS SUMBAGSEL PAKET-II & PAKET-III - PT. PERTAMINA EP (MUSI – PAGARDEWA - MERBAU, SUMATERA SELATAN)

 

·          The main responsibilities are to coordinate project control activities in preparing Project Schedule and its related documents such as Schedule Level 2, Execution Plans, Manpower Planning, etc.

 

PROPOSAL PROJECT CONTROL COORD.Apr.  2003 – June 2003

PROPOSAL OF DIENG & PATUHA GEOTHERMAL POWER PLANT (PT. GEO DIPA ENERGI / PT. BUMI GAS ENERGI – BANDUNG, WEST JAVA).

 

·          The main responsibilities are to coordinate project control activities in preparing cost estimate and technical document such as Project Budget, Project Master Schedule, Staffing Plan, Project Control Execution Plan, etc. Also responsible to review bid document, prepare clarification to client, and involved in clarification meeting

 

 

PREPARE FOR IN-HOUSE COURSE OF MASTER SCHEDULE

DEVELOPMENT USING PRIMAVERA  P3                Nov. 2002–Mar. 2003

 

THREE DAYS COURSE & WORKSHOP OF IN-HOUSE TRAINING OF PRIMAVERA PRACTICAL APPLICATION  (PT. IKPT, HRD).

 

·          The responsibilities are to introduce Project Control staffs to the optimizing use of Primavera P3 in practical application. Training will be intended to the use of Primavera P3 in generating critical path.

 

CERTIFIED TRAINER FOR IN-HOUSE COURSE OF       Mar. 2002–Nov. 2002

INTEGRATED PROJECT CTRL SYSTEM USING PRIMAVERA  P3      

 

THREE DAYS COURSE & WORKSHOP (25 – 27 Nov. 2002) OF IN-HOUSE TRAINING OF PRIMAVERA PRACTICAL APPLICATION  (PT. IKPT, HRD).

 

·          The responsibilities are to introduce Project Control staffs to the optimizing use of Primavera P3 in practical application. Training subject adopts the application of advanced project control management system in an Integrated Project Control System (IPCS). Main concept of this training is implementation of Earned Value Performance Measurement concept by integrating cost and schedule parameter in controlling project activities.

 

 

PROJECT CONTROL PROPOSAL COORD. Nov.  2001 – Feb. 2002

 

PROPOSAL OF BANYU URIP FIELD DEVELOPMENT EPC-A (EXXON MOBIL – CEPU, CENTRAL JAVA).

 

·          The main responsibilities are to coordinate project control activities in preparing proposal package i.e. Master Schedule, Staffing Plan, Direct Manpower Loading, Project Control Procedures, etc. Also responsible to review bid document, prepare clarification to client, and coordinate weekly meeting.

 

FIELD PROJECT CONTROL MANAGER                 April 1999 – October 2001

 

CENTRAL GATHERING STATION AREA-10 PROJECT (PT CALTEX PACIFIX INDONESIA) – DURI, RIAU. 

 

The responsibilities are to manage and coordinate day-to-day activities of Field Project Control i.e. planning & scheduling, progress monitoring, quantity surveying, cost controlling, meeting & reporting, computer system, and document controlling.  Conducting inter-department interface and information / data exchange through intensive discussion, meeting and reporting. Communicating and co-ordinating with Home Office Project Control Team for the Construction Status in relation with Engineering and Procurement Status. The general responsibility is to control overall tasks in order to maintain Project Milestones through good preparation, accurate planning, intensive monitoring, comprehensive evaluation, and corrective action. Other responsibilities are to control project changes, and to prepare project close out.

 

** Diverse of Nationality Environment : America, Korea

 

 

PROJECT CONTROL PROPOSAL COORD.                  Oct. 1998 –  Apr. 1999

 

PROPOSAL OF CENTRAL GATHERING STATION AREA-10 (PT CALTEX PACIFIX INDONESIA) – DURI, RIAU.

 

The responsibilities are assisting Proposal Co-ordinator in preparing and compiling package of Technical and Commercial Quotation. Developing proposal requirement data for Project Control section, those are Master Schedule, Staffing Plan, Direct Manpower Loading, and Project Control Procedures. Attending Pre-bid Meeting and Bid Opening. Review and study Contract Document prior to Contract Award.

 

SCHEDULING & PROGRESS COORD.                          May 1997 –  Oct. 1998

 

KUJANG 1B AMMONIA UREA PROJECT (PT PUPUK KUJANG)  – CIKAMPEK, WEST JAVA. 

 

The responsibilities for Scheduling were developing Project Control Execution Procedure, Schedule Control Procedure, Time Scaled Logic Network using Primavera Project Planner, Front End Schedule, Detailed EPC Schedule, and Manpower Planning. For Progress were developing EPC Progress Calculation Procedures, Progress Calculation sheet, curves and charts.

 

 

SCHEDULE ENGINEER                                            March 1997 –  April 1997

                       

BONTANG LNG EXPANSION TRAIN-H PROJECT (PT BADAK LNG) – BONTANG, EAST KALIMANTAN .

 

The responsibility was to support and advise Scheduling Team in developing Construction Schedule, Logic Network Diagram by using Primavera Project Planner. Giving advice in the preparation of Client Primavera Training Program.

 

 

PROPOSAL ENGINEER                                               Jan. 1997 –  March 1997

 

KALTIM PRANA INDUSTRY (KPI) – KALIMANTAN. 

 

The responsibilities were reviewing Tender Document requirement list, preparing proposal package. Developing proposal requirement data for Project Control section, those are Master Schedule, Staffing Plan, Direct Manpower Loading, and Project Control Procedures.

 

 

 

SCHEDULING & PROGRESS COORD.                       Jun. 1996 –  April 1997

 

VINYL CHLORIDE MONOMERE (PT SATOMO INDOVINYL MONOMERE) – MERAK, WEST JAVA. 

 

The responsibilities were monitoring and updating daily EPC Progress and Schedule status. Reporting Manhours expense and evaluating Manpower Productivity. Recording Project Outstanding Items and giving advise regarding schedule matters. Preparing Minutes of Project Management and Project Control Meeting. Preparing Close out report.

 

** Diverse of Nationality Environment : France

 

 

Dec. 1995 – May 1996                                              PT. PEDICINAL, JAKARTA

 

CONSTRUCTION SITE RESIDENT ENGINEER                               

 

PEMGEMBANGAN PEMUKIMAN TRANSMIGRASI (DEPTRANS) – AMBON, MALUKU. 

 

The responsibilities are managing and coordinating day to day activities at Ambon Site Office. Conducting Site Survey for problem identification and progress monitoring to the executing Contractors for Construction Management evaluation aspects. Prepare and issue Monthly Report to Jakarta Office.

 

 

Sept 1995 – Dec 1995              LAB CONSTRUCTION MANAGEMENT OF ITB

 

ENGINEER                                    

 

PEMGEMBANGAN PEMUKIMAN TRANSMIGRASI (DEPTRANS) – AMBON, MALUKU. 

 

The duties are Training Instructor of Construction Management Program for BNI 46 Construction Engineers . Assisting daily Lab CM activities, study Primavera, Ms Project and Artemis. Developing Cost Control calculation computer program using Database System.

 

 

Jul 1995 – Sept 1995                                     PT DINA MARITAMA, BANDUNG

 

PART TIME ENGINEER                             

 

The duties are developing Cost Account program using Database System. Updating project schedule status and preparing Monthly Report.

 

 

Sept 1994 – Dec 1994                                INSTITUT TEKNOLOGI BANDUNG

 

ON JOB PRACTICE                                   

 

·                Prepare report and scripts of Faculty’s new buildings development being under Construction. The report consists of Contractor’s Organization Chart, Work Progress, and Project Schedule.

Experience Hours (Planning & Scheduling): 
22050
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
7500

Market Place

No results found... (try selecting a different content filter)