Parsons Planner
START Date:
April, 1993
END Date:
November, 1995 Ralph M Parsons, AMOCO gas Project C.A.T.S. , Senior Planner
On assignment London Office
Develop Engineering/Construction Networks/plan
Level 3/2 and set up Project Controls for AMOCO gas Project C.A.T.S. Teesside, using Primarvera Software P3 for Windows working in an alliance framework with Contractors to jointly develop integrated plan for all disciplines.
Aug-1993 May-1995 Statoil, Kalundborg Condensate Project, Senior Planner
On assignment Kalundborg Condensate Project Maintain Construction Planning Network Levels 1, 2 and 3 Set up and maintain Commissioning Network Multiproject Linking of Networks Using Openplan software Version 5. Develop and maintain databases for work measurement and Project Status in specific Disciplines using Foxpro Software. Custom Reports in Openplan /
Foxpro Software Summary, Detail, "What if "Critical Path etc.
Graphic Reports S-curves, histograms etc. in Openplan /Freelance Software.
On assignment London Office
Develop Engineering/Construction Networks/plan
Level 3/2 and set up Project Controls for AMOCO gas Project C.A.T.S. Teesside, using Primarvera Software P3 for Windows working in an alliance framework with Contractors to jointly develop integrated plan for all disciplines.
Aug-1993 May-1995 Statoil, Kalundborg Condensate Project, Senior Planner
On assignment Kalundborg Condensate Project Maintain Construction Planning Network Levels 1, 2 and 3 Set up and maintain Commissioning Network Multiproject Linking of Networks Using Openplan software Version 5. Develop and maintain databases for work measurement and Project Status in specific Disciplines using Foxpro Software. Custom Reports in Openplan /
Foxpro Software Summary, Detail, "What if "Critical Path etc.
Graphic Reports S-curves, histograms etc. in Openplan /Freelance Software.
- Company:
- Industry:
- Region: