Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

DECON Engineering Ltd. Lead Planner

START Date: 
January, 2004
♦ WORK EXPERIENCE:

Apr 2009~Todate      DESCON ENGINEERING QATAR L.L.C

RAS GIRTAS POWER COMPANY (DESALINATION UNIT)

•     Level II and III Planning and Resource Loading using Primavera (P3).
•     Formulation of WBS and mapping of BOQ with Cost Centers and WBS numbers.
•     Prepared Base Plan independently & on time using P3.

As a Lead Planning, Monitoring & Scheduling Engineer

•     Planning and monitoring all the construction activities for the Desalination Unit being built by EPC Contractor, HYUNDAI, KOREA & SIDEM, FRANCE

Major responsibilities include

•     Leading the team of Area Planners for all disciplines to prepare the Work front on monthly and weekly basis, to calculate the resources, consumable and direct material for said work fronts and to control their respective discipline efficiency while Monitoring Daily Progress and Reporting to client.
•     Making Bill of Materials and total material required. Coordinate with Purchase department for in time material procurement and allocate the same to the Execution in consultation with store. Revised detailed Level 3 control schedule (Primavera P3) incorporating the physical status and all change orders.
•     Revised the drawings and document register used at level 4 to ensure all were identified and entered for the basics of scope. Review and advice on actions required for recovery on procurement schedules from the contractors, to meet delivery at site for the onsite required dates. Prepare scenarios to show the impact of Modifications & Late Material Supply to the completion of the Project.
•     Liaise with Sub Contractors Planning Engineers, for establishing their schedules and reports required to control their own scope. Validate all schedules upon submission for baseline; approve all subsequent progress/updates. Prepare Trend and forecast reports, Weekly and Monthly reports for Management.

Jan 2008~Apr 2009     DESCON ENGINEERING QATAR L.L.C

RAS LAFFAN OLEFIN PROJECT

As a Junior Planning & Monitoring Engineer
Planning and monitoring all the construction activities for the Cold Section of Ethylene Cracker Project (3rd Largest Project of its kind in the World) being built by EPC Contractor, TECHNIP FRANCE.

Major responsibilities include

•     Leading the System Administration of Descon Project Management Systems including the modules of DPMS (Descon Progress Monitoring System), DCS (Document Control System), ITS (Inspection and Test System), Test Pack, Bottlenecks, GDMS (Gainful Deployment of Manpower System).

•     Maintaining all the daily site progress, gradual monitoring and allocating the project materials, logistics routes and assigning the resources. Responsible for gathering the project remarks from the site engineers and update the same to the site project manager. Assigned to find the project delayed status. Preparing engineering plans, drawings, specifications and cost estimates. Responsible for analyzing the original status of the project and to find the CPM (critical path method). Preparation of Organization Chart. Preparation of Daily Progress Report and Analysis with our Bar Chart. Comparing The Daily, Weekly, Monthly Progress Back Logs. Collecting the practical difficulties of the project from site engineers and submitted to the Project Manager. Preparing & Maintaining of ISO Documents & Records. Updating of total documentation and facing the ISO Internal Audit.


2004~2007 Shakarganj Mills Limited (Jhang)
Shakarganj is a leader in Sugar Industry.
Features: 1- Sugar plant production more than 800 tons/day, 2- Self power generation of 30 MW, 3- Alcohol plants production more than 2 lack liters/day,
     As a Management Trainee
I worked in various disciplines of the industry to understand the process and the company policies.
Operation & Maintenance Planning Engineer
• To manage shift staff, independently, to maintain the following systems: a- Mill House b- Boiler House c- Power House and the relative maintenance of these houses. Allocation of work at various levels on different machines with the help of Gantt chart, and monitoring the production if the same has been achieved. Coordinate with Purchase Dept. for the requirement of materials and allocate the same to the production. d- Responsibilities include regular inspection of assigned equipment, participating in breakdown analysis/trouble shooting to minimize down time.
• Maintenance of Valves, Compressors, Pumps etc..
• I also act as a Technical Coordinator for marketing department to analyze competitor’s planning’s & strategies, customer market and buyer behavior.




Achievements:

• Successful implementation of HSE Policies
• Erection & commissioning of 5x6 MW Back Pressure Turbines & 3x6 MW Condensing Extraction Turbines.
• Erection & commissioning of a Steam Boiler of capacity 80Tons/Hr @ 25 Kg/cm2

2002     As an Internee
Done my internship in all the division of Millat Tractor Limited, Lahore

2001     As an Internee
4 weeks internship at Shakarganj Mills Ltd Jhang

Membership     Member of Pakistan Engineering Council (PEC)

Workshops      Participated in workshops on i) Fuel Conservation Techniques
      ii) Bearing Maintenance iii) Attitude, Communication and Team Work
♦ SKILL PROFILE:

Communication English, Urdu, Arabic
     
Computing      Technical
Primavera Project Planner (P3), MS Project, well conversant Auto CAD

Word Processing
Microsoft Word, Power Point, Excel spreadsheets

Study Projects     • “The study of engine division, manufacturing process, assembly line & quality analysis of MILLAT TRACTORS Ltd”
• Study of combined cycle power plant

Interpersonal Skills: Motivated & Professional, with natural drive, together with sound knowledge and a desire to succeed in developing capability in the field of Project Management and Control.