Planning Manager, Senior Planner, Larsen & Toubro Construction Co. KEO Internationl Consultant, ABB Lumus Global Corp., High Rise Building, Metro Rail, Petrochemechal & Refinery, Aiports and Infra
SUMMARY OF EXPERIENCE:
Thirty One years of continuous experience in Project Management, Construction Management and General Contractors as Planning Manager, Senior Planner /Senior Cost Estimator and Senior Quantity Surveyor. The projects that I was involved with are Metro Rail, High-Rise Buildings, Refinery, Petrochemical and Terminal Airport, Hospitals, Pipelines & Pumping stations, Utility Tunnels/Micro Tunneling and Infrastructure projects. Responsible in setting up Project Control concept,Planning and Scheduling, Cash Flow plan analysis, project estimating, and evaluation of contractor’s interim payment, and project supervision.
I.
January 2012 to Present
Larsen & Toubro Construction Pvt. Ltd.
Planning Manager
Project Undertaken:
- U$ 120,000,000– 75th Story Minerva Tower – Mumbai, India
- U$ 130,000,000 – Mixed Use Development Consisting of (5) 45 Floors Apartment Buildings, (2) 40 Floors Apartment Buildings and Centralized Basement Car park (for 4500 Cars) – Kolkata, India
- U$ 1,100,000,000– 72kms Hyderabad Metro Rail, Phase 1 – Hyderabad, India
Job Description:
- Develop/Prepare Project Baseline Schedule using P6/P3 (Primavera program) with resources and cost loaded, and Prepare Over-all Project Progress S-Curves, Cash flow plan and Progress Trend for Concrete for structural works monitoring.
- Coordinate/follow-up with the Project/construction managers the outcomes/progress status based on the three weeks look ahead schedule (rolling).
- Monitor the Projects progress against programmed milestones and implement delay recovery actions.
- Responsible for reviewing, checking and insuring that the projects are being planned controlled and reported on in the appropriate manner.
- Proactively identify and highlight any progress issues which threaten successful delivery of the project, so that recovery action may be taken.
- Provide functional support and guidance to more junior staff to develop both them as individuals and the capability of the team as a whole.
- Prepare progress reports with programmed analysis and recommendations, addressing programme issues to insure timely project completion.
- Keep Project Management fully informed on matters related to their area of responsibility so that decisions can be made based on the best available information.
II.
February 2008 to December 2011
KEO International Consultants
Senior Planner
Project Undertaken:
- QR 380,00,000– North & South Infrastructure Priority Package, Education City Project(almost completed) – Doha, Qatar
- QR 950,303,460– North/South Site Utility Tunnels, Education City Project (completed) – Doha, Qatar
- QR 880,000,000–National Convention Centre Car park, Education City Project - (completed)– Doha, Qatar
- QR 291,563,788– General Electric Advance Technology Research Centre, Education City Project (completed) – Doha, Qatar.
Job Description:
- Assist, provide guidance to contractor scheduling staff and assess contractor capability.
- Develop resource requirement to execute Program build with detailed time writing of various resources.
- Coordinate where required a fully integrated overall Planning and reporting function to provide support to the various Project groups (Engineering, procurement and contracts, construction, Commissioning and start-up to ensure that project management’s requirements for timely and accurate reporting of project activities is achieved
- Review the contractor's progress. Identify constraints and recommend corrective measures.
- Prepare project wide monthly/weekly schedule and progress reports and graphical presentations of the summary Plans and forecasts for appropriate input to the Project Monthly Reports, general Project ‘Visibility’ and any ad hoc reports that may be called for from internal or external sources.
- Coordinate and administer the overall Project Planning Trend and Revision System, and conduct the Trend and Forecast review meeting under the chairmanship of the Planning Department at least on a monthly basis, but more frequently as required.
- Keep Project Management fully informed on matters related to their area of responsibility so that decisions can be made based on the best available information.
- Review Contractors Execution Program to insure that it is compatible with the Project Method Statement, it comply with the contract milestone dates. Material/Shop drawings submittal, procurement and construction are adequate and integrated together.
- Set up Monthly Executive report, over-all progress S-curves chart, manpower histogram, and cash flow plan and productivity performance index.
- Monitor and update the actual progress of work in comparison with the schedule and highlight any discrepancies that may affect the completion of the works according to the established milestone dates.
- Evaluate Contractors Extension of time claims in substantiation of Change order that have time impact.
- Configures, maintains and administers cost control system and effective interfaces between cost control and project master schedule.
- Assess the impact of approved changes and any deviations from the key project targets and milestones, including productivity monitoring to aid project management decision-making.
III.
November 2006 to February 2008
PAKGULF Construction (Pvt) Ltd.
Planning Manager
Project Undertaken:
- U$380,000,000– Centaurus Mixed Use Development Consisting of(2) 26 Floors Apartment Buildings, (1) 23 Floors Office Bldg., (1) 35 Floors Hotel (7 star), 5 Floors Mega Mall, 3 Floors + 1 Mezzanine, Car park and External Landscaping – Islamabad, Pakistan
Job Description:
- Review Contractors Execution Program to insure that it is compatible with the Project Method Statement, it comply with the contract milestone dates. Material/Shop drawings submittal, procurement and construction are adequate and integrated together.
- Responsible for preparation of master detailed construction schedules using primavera project planner software and over-all progress chart showing S-curves and manpower histogram in excel, shop-drawing schedule, procurement schedule. In addition, cash flow plans.
- Monitor and update the actual progress of work in comparison with the schedule and highlight any discrepancies that may affect the completion of the works according to the established milestone dates.
- Assist and coordinates the preparation of project cost estimates. Ensures that the cost estimate reflect project WBS.
- Configures, maintains and administers cost control system and effective interfaces between cost control and project master schedule.
- Conduct specific cost analysis, reports and project information as required.
- Provide guidance to contractor scheduling staff and assess contractor capability.
- Provide remedial and preventive recommendations to the Project Management Team to ensure all milestone dates are met.
- Prepares monthly progress reports.
IV.
March 2004 to October 2006
Al Rashid Trading & Contracting Co.
Senior Planning Engineer
Project Undertaken:
- SR273, 310,773- Dammam 400 Bed Maternity & Pediatric Hospital, Dammam K.S.A
- SR 84,705,419- King Faisal University College of Medicine, Dammam K.S.A
- SR350, 000,000- Al Rashid Mall Expansion, Al Khobar K.S.A
Job Description:
- Study tender documents consisting of contract conditions, drawings, B.O.Q and specification.
- Coordinate with Tendering Departments Engineers to come up with a competitive and technically sound bid proposal.
- Responsible for preparation of all construction schedules for tender and ongoing projects, time scaled logic diagram using primavera project planner software and construction progress chart showing S-Curves and manpower histogram in excel & prepare cash flow plan, shop drawing schedule and procurement schedule.
- Update Master Project Schedule (P3), Shop Drawing Schedule, Procurement Schedule every end of the month and distribute to relevant divisions, PM, Client/Consultant.
- Monitor and update the actual progress of work in comparison with the schedule and highlight any discrepancies that may affect the completion of the works according to the established milestone dates.
- Provide remedial and preventive recommendations to the Project Management Team to ensure all milestone dates are met.
- Prepares monthly Project Management Construction Reports on all projects for submittal to the Construction Operation Manager.
V.
January 2001 to March 2004
Almabani General Contractors Co.
Sr. Planning/Cost Engineer
Project Undertaken:
- SR300, 000,000- SABIC Technology Center, Jubail K.S.A
- SR280, 000,000Prince Sultan City for Humanitarian Services, Riyadh K.S.A
Job Description:
- Study tender documents consisting of contract conditions, drawings, B.O.Q and specification.Responsible for monitoring and control of ongoing projects.
- Responsible for preparation of all construction schedules, time scaled logic diagram using primavera project planner software and construction progress chart showing S-Curves and manpower histogram in excel & prepare cash flow plan.
- Coordinate with Studies Departments Engineers to come up with a competitive and technically sound bid proposal.
- Development and management of detailed schedules covering activities through to the start of operation. Develop and implement progress measurement systems, progress measurement productivity trending and forecasting is effective and consistent.
- Monitor and update the actual progress of work in comparison with the schedule and highlight any discrepancies that may affect the completion of the works according to the established milestone dates.
- Provide remedial and preventive recommendations to the Project Management Team to ensure all milestone dates are met.
- Coordinate with the Consultant (DAR) on matters relevant to the project planning and cost control.
- Prepare monthly interim payment and monthly progress reports for submittal to the consultant.
- Reports to the Project Manager
VI.
February 2000 to December 2000
SEIMENS Philippines
Project Planner
Project Undertaken– U$580,000,000-Construction of NAIA III Terminal Airport, (Philippines)
Job Description:
- Responsible for preparation of overall electro-mechanical construction schedules, time scaled logic diagram using primavera project planner software and construction progress chart showing S-Curves and manpower histogram in excel & prepare cash flow plan.
- Configures, maintains and administers cost control system and effective interfaces between cost control and project baseline schedule.
- Evaluate Sub-Contractors monthly interim payments and Prepare monthly progress reports.
- Monitor the actual progress of work in comparison with the schedule and highlight any discrepancies that may affect the completion of the works according to the established milestone dates
- Project Planning and Scheduling expertise to Project Engineers in the development and maintenance of the activities, logic, resources and progress of the approved integrated project schedule against the baseline in accordance with Planning and Scheduling Guidelines.
VII.
January 1999 to January 2000
ABB Lummus Global Overseas Corp.On secondment to J.A Jones Inc
Senior Cost Engineer
Project Undertaken– Coastal Refinery Expansion Project & Construction of 30MW Power
Plant,(Aruba Netherlands Antilles).
Job Description:
- Formulating, developing and applying advanced cost control concepts. Determine and manage project cost breakdowns and cost allocation. Assist in global changes of master baseline schedule using primavera project planner (P3).
- Responsible for preparation of project cost estimates. Ensures that the cost estimate reflect project WBS.
- Configures, maintains and administers cost control system and effective interfaces between cost control and project master schedule.
- Quantity Take-off on Mechanical and & Electrical works, Tracking Work Orders Log regarding sub-contractor hour and cost & TCN hours under the supervision of J. A. Jones.
- Evaluate Sub-contractors monthly valuation and assign cost coding to invoices for cost control purposes.
- Deliver timely, accurate and sensitive project controls information that facilitates a clear understanding of the performance of the project in relation to planned performance targets on behalf of the Client.
- Deliver timely, accurate and sensitive project controls information that facilitates a clear understanding of the performance of the project in relation to planned performance targets on behalf of the Client.
VIII.
August 1996 to December 1998
Kelip Bintang Sdn Bhd
Sr. Planning Engineer / Sr. Quantity Surveyor
Project Undertaken–Mixed Development consisting of residential houses, commercial
buildings, hotels, and infrastructure.(Kuala Lumpur, Malaysia).
Job Description:
- Prepare work breakdown structure, manpower histogram and formulate overall project master schedule. Set-up cost control system and prepare project cash flow plan and monthly progress chart.
- Development and management of detailed schedules covering activities through to the start of operation. Develop and implement progress measurement systems, progress measurement productivity trending and forecasting is effective and consistent.
- Tracking consultants’ design progress, contractors’ progress, analyzing critical path activities and update the project master schedule regularly.
- Manage consultants’ monthly fees payment and evaluate contractors’ monthly interim payments based on approved monthly progress of works. In charge of coordination with the Q.S. Consultant in formulating tender/contract documents and elemental cost estimates based on conceptual design for budgeting purposes.
- Provide remedial and preventive recommendations to the Project Management Team to ensure all milestone dates are met.
- Reports to the Project Manager
- Project Planning and Scheduling expertise to Project Engineers in the development and maintenance of the activities, logic, resources and progress of the approved integrated project schedule against the baseline in accordance with Planning and Scheduling Guidelines.
IX.
July 1995 to August 1996
Kuala Lumpur City Centre Bhd.
Senior Cost Estimator
Project Undertaken – Petronas Twin Towers, (Kuala Lumpur Malaysia)
Job Description:
- Responsible on the overall project cost estimation and management of contract. Analyze and review the contractors planning/ scheduling. Prepare project cash flow and set-up cost control system; organize pre-measurements on civil works, structural, mechanical, and electrical works.
- Assist in the pre-qualification of potential tenderers and to analyze tenders in accordance with the requirements of the company procedures.
- Monitor progress accomplishment, evaluate monthly valuation of contractors and agree interim payments for approval by the project manager
- Deliver timely, accurate and sensitive project controls information that facilitates a clear understanding of the performance of the project in relation to planned performance targets on behalf of the Client. .
- Facilitate appropriate management intervention in order to maintain planned performance, reduce and/or mitigate performance degradation.
- Contribute to the forecasting of the project’s Anticipated Final Costs (based on an understanding of the final integrated – time, cost and scope – position)
X.
April 1994 to May 1995
Saudi Designers
Senior Cost Estimator
Project Undertaken – Commercial Buildings & Villas,
Job Description:
- Contracts Administration, monitoring financial status of project inclusive of conceptual estimating, cost analysis, estimate coordination and consolidation. Prepare inquiry documents and subcontract documents.
- Assist in the pre-qualification of potential tenderers and to analyze tenders in accordance with the requirements of the company procedures. Monitor progress accomplishments and evaluate monthly interim payment of the contractors.
- Prepare variation orders for issuance by the project manager and to agree the value of variations for approval by the subcontract manager or his deputy and prepare monthly financial and design progress reports.
- Foster the evolution of a project controls culture across the Client Management team, as well as the nominated Designer, that support attainment of the schedule’s performance.
- Facilitate effective working practices and relationships with the commercial, cost, planning, production teams, which support the success of the integrated controls function.
XI.
April 1992 to October 1993
John Brown Saudi Arabia Limited
Cost Engineer/Quantity Surveyor
Project Undertaken – Construction of Polyethylene Plant, (Jubail K.S.A)
Job Description:
- Take measurements on civil works, structural and steel works architectural & mechanical works in accordance with the standard method of measurements for civil engineering and industrial engineering construction.
- Set-up cost control system and prepare project cash flow plan and monthly progress chart.
- Review and verification of subcontractors’ interim payment invoices and insuring compatibility between works executed and payment claimed.
- Monitor progress accomplishments, agree the value of day works for approval by the contract manager, and prepares monthly financial reports.
XII.
March 1990 to March 1992
Al-Taqadum Est. for Cont. & Trade
Planning Engineer / Quantity Surveyor
Project Undertaken – Construction of 6 storey apartments & villas, (Yanbu K.S.A)
Job Description:
- Responsible in the preparation of Project Master Schedule, cash flow plan and monthly progress chart. Verifies conformity of project execution with the design, plans, specification, schedules and budget cost.
- Prepare quantity and material take-off on civil works, structural, architectural, mechanical & electrical works for bidding and site implementation purposes.
- Organize work planning and method, preparing detailed progress reports concerning site developments, evaluates work schedule and cost.
- Monitor daily progress accomplishments and prepares monthly invoice and monthly progress reports.
- Update the actual progress of work in comparison with the schedule and highlight any discrepancies that may affect the completion of the works according to the established milestone dates.
- Keep Project Management fully informed on matters related to their area of responsibility so that decisions can be made based on the best available information.
XIII.
January 1987 to January 1990
Al-Watad Establishment
Planning Engineer/Estimator
Project Undertaken – Construction of Industrial building & villas, (Yanbu K.S.A)
Job Description:
- Prepare work breakdown structure, manpower histogram, two months look-ahead, cash flow plan and project monthly progress chart. Taking control of the site and entire works, identify sequence of operation and plans sequence of execution.
- Prepares project estimate, materials quantification, preparation of bill of quantity & cost estimate through value engineering.
- Monitor daily progress accomplishments and prepares monthly invoice and monthly progress reports.
- Project Planning and Scheduling expertise to Project Engineers in the development and maintenance of the activities, logic, resources and progress of the approved integrated project schedule against the baseline in accordance with Planning and Scheduling Guidelines.
XIV.
January 1982 to October 1986
Apex Philippines Construction & Dev. Corp.
Project Engineer/Estimator
Project Undertaken – Commercial Buildings, Bridges, Water Supply, Roads & Highways, Philippines
Job Description:
- Manage the allocation, monitoring, construction management, and projection of resources: staff, manpower, plant and equipment on the whole development.
- Inspection of daily construction activities including special processes.
- Check quality control documentation which includes preparation of pour cards, hold point release, materials test report, Quality Control report.
- Organize daily, weekly and monthly reports and meetings with team members, subcontractors, consultants, and clients.
- Review and evaluate of any potential cost deviation of site instruction. Review and evaluate of any potential contract addition/modification and works changes as per RFI and Prepare cost detailed estimates.
- Review Sub-contractors Execution Program to insure that it is compatible with the Project Method Statement, it comply with the contract milestone dates. Material/Shop drawings submittal, procurement and construction are adequate and integrated together.
- Provide remedial and preventive recommendations to the Project Management Team to ensure all milestone dates are met.
SEMINARS/TRAINING ATTENDED
Primavera Planning & Scheduling Conducted by - Primavera System/
Advance Topic (June 23-25, 1997) HSS Intesys Sdn. Bhd. Selangor, Malaysia
Construction Planning and Management Conducted by - National Housing Authority
April 15-18, 1984 Manila, Philippines
COMPUTER LITERACY:
Primavera P6 and P3
Primavera Sure Track
MS Project
Track 2000
MS Power Point
Microsoft office Word
Microsoft office Excel
CITIZENSHIP: Filipino
EDUCATION: Bachelor of Science in Civil Engineering (1985)
FEATI University, Manila Philippines
DATE OF BIRTH: October 10, 1955
Contact Address: +918886997820 and Philippines Mobile +639052145049
E-mail:crldiez_012@yahoo.com
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: