Planning (Scheduler) Engineer, Marubeni Corporation (Qatar), GTC/124/2006/C Phase 7, GTC/117/006 220kV & 66kV, GTC/14/2003 Phase 5

START Date: 
May, 2006
END Date: 
March, 2007

Responsibilities:

  • Prepared Project Execution Program that consist of Baseline Schedule, Engineering Register, S-Curves and Histograms.
  • Prepared Project Cash Flow, Budget Cash Flow and quantity take off.
  • Prepared schedule analysis of supplier’s delivery commitments and revised proposal to meet project completion date.
  • Monitor and prepare weekly progress reports, monthly progress reports and management meeting reports.
  • Assist in preparing submissions for approval such as Method Statements, Material Specifications, Technical Design and Drawings.
  • Assist in evaluation of subcontractor’s billing and organizing project documentation.

Project Involved:

  • GTC/124/2006/C Phase 7 – Cables (Qatar)
  • GTC/117/2006 220kV & 66kV Cables (Qatar)
  • GTC/14/2003 Phase 5 – Cables (Qatar)
Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Forensic Analysis): 
1800