Hi Friends,
In one of my projects I prepared a resource loaded programme in P6. And after few days I levelled the resource using level resource option in P6 and the Project finish date is changed to Jan 2018 from Nov 2017.
And my problem is unfortunately I didnot copy the first progremme (not resource levelled) and I levelled the resource.
I need my first programme (finishing on Nov 2017); How can i get it? Is there any options in P6 like "Relevel the resource " or something else?
Please help me.
Thanks
Dixit