Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Primavera

Hi Guys,

Can anyone suggest a reason why the original duration might be one day and the start and finish dates show as two days. See example below. 

Start: Oct 08th Finish: Oct 09th

 

Thanks in advance.

Comments

Check the Clalendar set for

Check the Clalendar set for the Activity. if the Calendar is set at four hour duration and original duration is 8 hours then it will show as 2 dates.

Market Place

No results found... (try selecting a different content filter)