delayed due to the lack of Resource

Hi everyone, i have a doubt about schedule result on Spider Project. My schedule is niveled for some resources and in a make reprogramation of activities for a simulation for aceleration schedule and after scheduling by RCP the message was "Activity "DÉBLAI | TRONCON 1 - (55+925 a 85+900)" (Code: TER07) is delayed due to the lack of Resource "ESCAVADEIRA HIDRAULICA SOBRE ESTEIRAS" (Code: F1)" and "Activity "DÉBLAI | TRONCON 1 - (11+000 a 33+000)" (Code: TER04) is delayed due to the lack of Resource "ESCAVADEIRA HIDRAULICA SOBRE ESTEIRAS" (Code: F1)".wysiwyg_imageupload:: I'm very curious to know what exactly mean this message because I couldn't find the problem.

7296
spider_rcp.png

7295
spider_rcp_2.png

 

 

 wysiwyg_imageupload::

Comments

Resource Dependencies

Ok Mr. Liberzon, I set options and saw the informations but, something called my attention, observe below:

In the last activity, the field "reason of delay" don't filling and don't show the link "resource dependencies", why this happened ? What the criteria that Spider used? If all activities uses the same resource?

Resource Dependencies

Ok Mr. Liberzon, I set options and saw the informations but, something called my attention, observe below:

In the last activity, the field "reason of delay" don't filling and don't show the link "resource dependencies", why this happened ? What the criteria that Spider used? If all activities uses the same resource?

Resource dependencies

Daniel,

Spider Project can also show the reasons for delays by resoure dependencies.

If you will select Create resource dependencies in the scheduling oprions and Show resource dependencies in the Gantt Chart settings then dotted arrows will show why activities in resource constrained schedules are delayed.

Best Regards,

Vladimir

Ok Mr. Liberzon, I did

Ok Mr. Liberzon, I did understand, i thought it would that some errors on my schedule, but this message only explain the calculus, thanks .

Resource Gantt Chart

Please open Resource Gantt Chart and run simple scheduling (without resource leveling).

You will see that resource VIBROACABADORA DE ASFALTO SOBRE ESTEIRAS 700T/H works on a lot of parallel activities.

After leveling some of them are delayed to avoid resource overload.

delayed due to the lack of Resource

Hi,

In the beginning of this year Mr. Liberzon answer question about "delayed due to the lack of resource". Now I faced again some problem but different way, I Think.

Now, Spider acuses that happen delayed of resouce "Vibroacabadora Code:B2" but it happens that no activity are in parallel. What could be happening?

 

In wetransfer, the file.

https://we.tl/t-M5pvv8hfbv

Thank you in advance.

Daniel Crisóstomo

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Understood

Thank you very much Mr. Liberzon, perfectly understood.

It looks like Resource

It looks like Resource "ESCAVADEIRA HIDRAULICA SOBRE ESTEIRAS" (Code: F1)" was assigned to activities DÉBLAI | TRONCON 2 - (00+000 a ??+???), DÉBLAI | TRONCON 1 - (55+925 a 85+900) and DÉBLAI | TRONCON 1 - (11+000 a 33+000). And so these activities could not be done in parallel. To solve resource conflict the start of activity DÉBLAI | TRONCON 1 - (11+000 a 33+000) was scheduled after the finish of activity DÉBLAI | TRONCON 2 - (00+000 a ??+???) and activity DÉBLAI | TRONCON 1 - (55+925 a 85+900) starts after finish of activity DÉBLAI | TRONCON 1 - (11+000 a 33+000).

In this schedule resource "ESCAVADEIRA HIDRAULICA SOBRE ESTEIRAS" (Code: F1)" is not overloaded.

If you will run simple scheduling ignoring resource constraints activities will not be delayed but resources will be overloaded.