Change in original duration
Original duration in my baseline programme is of 1069 days. When i assign and maintain this baseline into a similar programme in which i am updating the progress, the original duration is changing to 1469 days. I believe the duration has to be the same as of baseline.
FYI: The baseline start and Finish are intact but the problem is only with the duration.
Pls help
Groups:
- Printer-friendly version
- Login or register to post comments
- Send to friend
Comments
Change in original duration
What software do you using?
Did you check the calendar?
Try:
https://ccsspl123-public.sharepoint.com/Support%20Documents/DIFFERENT%20...
https://p6primavera.wordpress.com/topics/topic-3-activity-types/
https://tensix.com/2015/07/resource-dependent-activity-type-in-primavera...