Change in original duration
Original duration in my baseline programme is of 1069 days. When i assign and maintain this baseline into a similar programme in which i am updating the progress, the original duration is changing to 1469 days. I believe the duration has to be the same as of baseline.
FYI: The baseline start and Finish are intact but the problem is only with the duration.
Pls help
- Printer-friendly version
- Login or register to post comments
- Send to friend
Comments
Change in original duration
The difference in days between both durations are 400 days, and from the original duration 1069 days is around 3 years
if the first calendar works on 5 days basis and the other calendar works on 7 days basis, the difference make (52*2*3)312 days, the other 88 days are due to the holidays assignment difference in both calendars throughout the 3 year of original duration.
Change in original duration
Can you check the calendars used by both schedules? It looks like one schedule uses a 5 days / week calendar and the other a 7 days / week calendar.