#Planning Engineer #Planning #projectcontrols # construction #build #residential, China Energy Engineering Construction Group Zhejiang Thermal Power Construction Company Limited, China Huaneng Yuhuan 4X1000MW power plant

START Date: 
July, 2006
END Date: 
November, 2007
Turbine engineer of the first 1000MW Power plant in China from construction company. Mainly work is the process control for turbine installation.
Experience Hours (Planning & Scheduling): 
2000

Cost and Field Engineer, Newco Builder and Development Corporation, Various Hospitals and roads constructions

START Date: 
January, 1998
END Date: 
May, 2001

 

 

Experience Hours (Planning & Scheduling): 
3200
Experience Hours (Cost Management): 
3200

Planning Engineer, Gammon Construction Limited, LUCITE INTERNATIONAL, ALPHA 1 PROCESSING PLANT PROJECT , CONSTRUCTION of the ITE COLLEGE (WEST) PROJECT

START Date: 
October, 2007
END Date: 
February, 2010

·       Support for the Project Manager and other specialty engineers with coordination on project planning, scheduling and program controls

·       Analyze the baseline schedule, check links and critical path, comment on the suitability of the schedule, point out errors and oversights.

·       Tracking all activities on site

Project Planner, Thales Australia, OneSky Air Trsffic Management System

START Date: 
November, 2017
END Date: 
October, 2018

Planning & Scheduling on the One Sky Air Traffic Management system

Project Planner, Thales Australia, OneSky Air Trsffic Management System

START Date: 
November, 2017
END Date: 
October, 2018

Planning & Scheduling on the One Sky Air Traffic Management system

Senior Planning Manager, Trans Adriatic Pipeline Ag, Trans Adriatic Pipeline

START Date: 
March, 2013
Senior Planning Engineer (Manager) Strategic planning, Master Control Schedule, Project controls
Experience Hours (Planning & Scheduling): 
14050
Experience Hours (Cost Management): 
6550
Experience Hours (Forensic Analysis): 
2600

Senior Planning Manager, Trans Adriatic Pipeline Ag, Trans Adriatic Pipeline

START Date: 
March, 2013
Senior Planning Engineer (Manager) Strategic planning, Master Control Schedule, Project controls
Experience Hours (Planning & Scheduling): 
14050
Experience Hours (Cost Management): 
6550
Experience Hours (Forensic Analysis): 
2600

Senior Planning Manager, Trans Adriatic Pipeline Ag, Trans Adriatic Pipeline

START Date: 
March, 2013
Senior Planning Engineer (Manager) Strategic planning, Master Control Schedule, Project controls
Experience Hours (Planning & Scheduling): 
14050
Experience Hours (Cost Management): 
6550
Experience Hours (Forensic Analysis): 
2600

Project Planner, Marine Services Ltd, Consultancy

START Date: 
February, 2001
END Date: 
February, 2002

Summary of my responsibilities are:

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
1000

Dale Hendershot

First Name: 
Dale
Last Name: 
Hendershot

Mr. Hendershot is the founder and managing member of Hendershot Consulting, LLC (HC).He has thirty six (36) years of experience in various capacities at professional consulting firms, large commercial construction companies, government contractors and large insurance/surety companies.

Professional Since: 
May-1989 (35.9 yrs experience)
Oldest experience: 
Jun 2006 (18.8 yrs experience, WARNING: 17.1 years variance with Professional Since)
Years Experience: 
29