Project and tender planning.

Senior Planner, Birse Rail, Trent Valley 4 Tracking (TV4T) & Rugeley Eastern Bypass

START Date: 
June, 2005
END Date: 
September, 2005

Project planning on the TV4T project ‘River Tame Structures Package’ which involved the structures and earthworks over and adjacent to the River Tame to enable the expansion of this part of the west coast mainline from 2 to 4 lines.

Senior Planner, Schofield Lothian, Various

START Date: 
October, 2005
END Date: 
December, 2006

Responsible for the development, implementation and handover of a P3e based project controls system for the £50 million per annum North West Gas Alliance.  This project was for the renewal of 400kms per annum of low and medium pressure gas mains together with service connections.  As well as managing the 6 planning consultants which developed the new controls system, I was also responsible for training the clients planning operatives to use new system.

Prepared a delay report for the civil engineering contractor on a £60 million rail re-signalling project in South Wales.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Forensic Analysis): 
950