Project and Construction Planner

Planning Engineer, Balfour Beatty Utility Solutions, Beauly to Denny 400kV new build OHL construction project

START Date: 
August, 2012
END Date: 
October, 2011

 

Planning Engineer on a £600m project to replace the existing 132kV Beauly – Denny transmission line with an upgraded 400kV line covering a 220km route including the erection of 600 new towers

Create update and maintain the project programme using Primavera P6 and communicate it to all relevant parties

Visit sectional site offices on a weekly basis in Beauly, Dalwhinnie and Crieff to update and report progress on a weekly basis to the Programme Manager and senior management team

Project and Construction Planner, First Quantum, KMT

START Date: 
November, 2008
END Date: 
November, 2009

 

I was the Project and Construction Planner for the construction and commissioning phases of a new copper & cobalt mine process plant in the DRC.  