Project Planner / Construction Scheduler, PT Freeport Indonesia, Deep Ore Zone 2nd Crusher

START Date: 
October, 2005
END Date: 
May, 2007

A brown field construction project for gyratory crusher installation at underground mining area as primary crusher to upgrade DOZ mining production from 35,000 metric tons per day to 50,000 metric tons per day.

As dedicated project Scheduler, responsible to provide detailing EPCC schedule, manpower & equipment resource planning. Representative of Project Control Department during project communication among Underground operation as client, Construction department as execution and CS engineering as drawing design provider.

Experience Hours (Planning & Scheduling): 
1700
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
150

Project Controls Specialist (EPC), Praxair Russia, Praxair 2xT1300 plant

START Date: 
September, 2010

Control and Analyse construction schedule of the project

Report progress and build/ maintain project s-curves

Track on-site manpower

Bid/Project Planning Engineer, Vinci Construction UK Ltd, A406 Hanger lane Bridge replacement project, Tender Planning

START Date: 
August, 2008

As a Planning Engineer for A406 Hangerlane Bridge project

Tender Planning - Energy Projects

Planning Engineer for London Bridge - Soil Engineering Project