Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Financial Analysis

Project Controls Analyst, Kiewit Power Constructors, Pio Pico Power Plant

START Date: 
April, 2013
END Date: 
May, 2014

Kiewit Power Engineers, Transmission & Delivery

Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Senior Project Services Engineer, SNC - LAVALIN INTERNATIONAL INC., Fired Steam Power Plant Project 300-400MW

START Date: 
December, 2008
END Date: 
December, 2009

Directly responsible for provision and coordination of all activities in the project including cost control, invoicing, variation claims, change management, planning, payment resolution, as well as the creation, negotiation, and management of contracts.  Managed project execution, stakeholder engagement,resource allocation, and governance processes throughout the project lifecycle.Analyzed reports for profitability, manpower productivity, efficiency, and resources.  

Experience Hours (Planning & Scheduling): 
650
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
1100

Controls and Planning Lead, Capgemini, Heathrow Terminal 2 Project

START Date: 
April, 2012

Lead Primavera P6 Planner on the Heathrow Terminal 2 Project

Controls and Planning Lead, Capgemini, Heathrow Terminal 2 Project

START Date: 
April, 2012

Lead Primavera P6 Planner on the Heathrow Terminal 2 Project

Construction Analyst/Project Scheduler, ecoseed, 1.Construction of Multistoried Buildings

START Date: 
December, 2008

a  p6 trainer  at  " AMIES it  academy   & cellection academy  and   MYACADEMY " for management 
 feasibility studies trainer  at MY academy 
 planning  instructor at my academy 
risk management  instructor   at My academy 

Project Controls (Budget/Schedule Engineer), Tefirom Group, Several Projects

START Date: 
April, 2011
END Date: 
September, 2011

- Take active role in tender stages of upcoming projects, analyzing the work schedule and technical details from a financial and commercial perspective, creating a budget plan which is dependent to duration and fiction of each single project.

- Analyzing the annual budget study and to determine if it is realistic, complete and cost-effective,

- Recommend on how the budget study could be improved to minimize waste and maximize efficiency,

Project Controls (Budget/Schedule Engineer), Tefirom Group, Several Projects

START Date: 
April, 2011
END Date: 
September, 2011

- Take active role in tender stages of upcoming projects, analyzing the work schedule and technical details from a financial and commercial perspective, creating a budget plan which is dependent to duration and fiction of each single project.

- Analyzing the annual budget study and to determine if it is realistic, complete and cost-effective,

- Recommend on how the budget study could be improved to minimize waste and maximize efficiency,

Project Cost Control Engineer, Greenstone Resources Corporation a member of Red 5 Limited, Siana Gold Mining Project

START Date: 
October, 2010

GREENSTONE RESOURCES CORPORATION (18 October - present)

A MEMBER OF THERED 5 LIMITED GROUP OF COMPANIES

L5, NOL Tower, Commerce Ave., corner Acacia Ave., Madrigal Business Park

Muntinlupa City, Philippines

www.greenstone.com.ph

 

  • SIANA GOLD MINING PROJECT/ SURIGAO DEL NORTE, PHILIPPINES

US$70M

 

PROJECT COST CONTROL ENGINEER

Market Place

No results found... (try selecting a different content filter)

Syndicate content