Lead/Senior Planning Engineer, Descon Engineering Limited, Mangla Dam Raising Project & Satpara Dam Project

START Date: 
October, 2003
END Date: 
July, 2007

•     Prepare and maintain CPM resource loaded programs for all phases of the engineering, procurement and construction work.
•     Prepare the daily progress reports for head office & for the consultant.
•     Prepare daily / weekly and monthly progress reports.
•     Based on updated progress, update the Project Level – III plan & import into DPMS software.