Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

& project planning 2)cost planning 3)feasibility study 4)primavera p6 6)

Lead/Senior Planning Engineer, Eni saipem, & Oil & Gas Projects Infrastructurus Storage tanks

START Date: 
August, 2013
END Date: 
March, 2015
-Baseline Time Schedule & Updates, Recovery Program, Optimized Plan, Impacted Schedule, Revised Baseline included all detailed activities for Engineering, Logistic, Procurement, Construction, Pre-commissioning and Commissioning Activities, -Construction Method Statement. -Mobilization plan for the resource Man-Power and Equipment on Monthly Basis for Camp Facilities and accommodation. -Reports to the Client (Daily Report, Weekly Report, Monthly Report, Cost Report, Invoices, Procurement Update, Material delivery Tracking Logistic, Executive Reports).
Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
1800
Experience Hours (Forensic Analysis): 
700

Lead/Senior Planning Engineer, Eni saipem, & Oil & Gas Projects Infrastructurus Storage tanks

START Date: 
October, 2013
END Date: 
March, 2015
-Baseline Time Schedule & Updates, Recovery Program, Optimized Plan, Impacted Schedule, Revised Baseline included all detailed activities for Engineering, Logistic, Procurement, Construction, Pre-commissioning and Commissioning Activities, -Construction Method Statement. -Mobilization plan for the resource Man-Power and Equipment on Monthly Basis for Camp Facilities and accommodation. -Reports to the Client (Daily Report, Weekly Report, Monthly Report, Cost Report, Invoices, Procurement Update, Material delivery Tracking Logistic, Executive Reports).
Experience Hours (Planning & Scheduling): 
2350
Experience Hours (Cost Management): 
1900
Experience Hours (Forensic Analysis): 
800

Lead/Senior Planning Engineer, SMI, & Oil & Gas Projects Infrastructurus Storage tanks

START Date: 
October, 2010
END Date: 
May, 2011
-Baseline Time Schedule & Updates, Recovery Program, Optimized Plan, Impacted Schedule, Revised Baseline included all detailed activities for Engineering, Logistic, Procurement, Construction, Pre-commissioning and Commissioning Activities, -Construction Method Statement. -Mobilization plan for the resource Man-Power and Equipment on Monthly Basis for Camp Facilities and accommodation. -Reports to the Client (Daily Report, Weekly Report, Monthly Report, Cost Report, Invoices, Procurement Update, Material delivery Tracking Logistic, Executive Reports).
Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
350
Experience Hours (Forensic Analysis): 
100

Area Planner, Black & Veatch, Banjarsari Power Plant Project 2x135MW

START Date: 
February, 2015

Experince

January 2015 – Until now

Company                        :Jaya CM as Consultant

Position                           :Planner and Scheduler

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
3000

Assistant Manager - Pm & Planning, İÇTAŞ, 12 High Ends Residential/Condominiums Building Project

START Date: 
May, 1991

From 5/1991 till 1/2008 :  worked as : site engineer, planner, project manager,  technical engineer, internal auditor, technical manager.

From 2/2008 till now : Supervision and management consultant .

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
22700

planning engineer, SEIDCO GENERAL CONTRACTING, Al Wagan Hospital Abudhabi

START Date: 
September, 2014

Planning Engineer

Planning Engineer

Planning Engineer

Planning Engineer

Planning Engineer 

Planning Engineer 

Planning Engineer 

Planning Engineer

planning engineer, SEIDCO GENERAL CONTRACTING, Al Wagan Hospital Abudhabi

START Date: 
September, 2014

 

Planning Engineer

 

 

v  Prepare project schedule (Base line).

v  Cost Loading.

v  S-Curve& Resources Histograms.

v  Monitor critical activities.

v  Updating progremme.

v   Showing Lookahead activities.

v  Prepare reports reflecting work progress.

planning engineer, SEIDCO GENERAL CONTRACTING, Al Wagan Hospital Abudhabi

START Date: 
September, 2014

Sr. Planning Engineer

 

v  Prepare project schedule (Base line).

v  Cost Loading.

v  S-Curve& Resources Histograms.

v  Monitor critical activities.

v  Updating progremme.

v   Showing Lookahead activities.

v  Prepare reports reflecting work progress.

project planner, HIJAZI CONSULTANTS, BAIL(BENGALURU INTERNATIONAL AIRPORT LTD) INDIA

START Date: 
April, 2010

>   Preparing and monitoring Project Schedules for efficient Project execution & timely completion

 

Ensure the Execution of the Project as per International Quality Standards

 

Strict adherence and implementation on the requirements of ISO

 

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Cost Management): 
3300

project planner, HIJAZI CONSULTANTS, BAIL(BENGALURU INTERNATIONAL AIRPORT LTD) INDIA

START Date: 
April, 2010

>   Preparing and monitoring Project Schedules for efficient Project execution & timely completion

 

Ensure the Execution of the Project as per International Quality Standards

 

Strict adherence and implementation on the requirements of ISO

 

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Cost Management): 
3300

Market Place

No results found... (try selecting a different content filter)

Syndicate content