North London Line Depot Planning Manager, Network Rail Ltd, Network Rail South East Territory

START Date: 
January, 2003
END Date: 
December, 2004
  • Work with the Depot Maintenance Manager, Engineers and Contractor's to identify local key maintenance tasks for the development of the annual work programme and annual possession plan.
  • Collate agreed annual volumes of work from area and depot, to produce a local annual work plan, which includes strategic possessions and key resources, in order to optimise both work and resources for agreement with the Area Delivery Planning team.
  • From the annual maintenance programme (signed-off by DMM) l developed the quarterly plan for my depot and identified long lead-times, resource
Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
950