Planner, WS Atkins, New Build - Defence Contractor

START Date: 
March, 2007
END Date: 
June, 2007

Planner in a large team for a Tier 1 contractor Designing and Building a new Testing Facility on a Large Dedence Site in Berkshire

Responsible for creation of a manhours loaded programme that involved the co-ordination activities accross 4 Regional Offices.

Liaison with the client Planner to ensure that Design tasks were completed or explained to the client ahead of the Master Programme being presented to the Clients board.

Experience Hours (Planning & Scheduling): 
500