Cost and Risk Management

STA to Project Director, AES Corporation, 2X660MW Thermal Power Project of AES OPGC

START Date: 
March, 2014
PMO Office set up and management for Engineering, Procurement and Construction of 2X660MW Super Critical Power Plant, 47KM Railway Network for Coal transsportation from Coal mine, Ash Pond Rroject and Township Infrastructure Developement. Establishment of Project Execution Plan and Project Control procedure in EPC set up till handover to operator. Monitoring and control for schedule, cost and risk.
Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
500