%100- Project Planning; Progress Reporting; MSP

Civil Project Coordinator, RVIPL, Project Management Consultancy for Sandesh City

START Date: 
September, 2012
END Date: 
April, 2015

1. Monitoring the schedules submitted by contractors and constantly checking the progress of work as per the schedule.

2. Responsible for the preparation of Project schedules

Experience Hours (Planning & Scheduling): 
5350

Assistant Manager - Planning, "Pratibha Industries Ltd, Mumbai", Augmentation of Water Supply Network in Navi Mumbai Municipal Corporation area under JNNURM Project for NMMC

START Date: 
March, 2012
END Date: 
August, 2012
  • Responsible for the preparation of Cash flows, Project schedules along with the manager.
  • Monitoring of cash flow and schedules.
Experience Hours (Planning & Scheduling): 
400

Assistant Planner or Planning Engineer, Simplex Infrastructures Limited, Construction of Multipurpose berth at Dahej for Adani Petronet Port Pvt Ltd

START Date: 
February, 2009
END Date: 
May, 2010
  • Responsible for the Planning and Scheduling of the project activity of Steel Piles (using MSP).
  • Monitoring the progress of the project.
Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
0

Programmer, Emico Ltd, Crossrail West Stations

START Date: 
May, 2016
END Date: 
April, 2017

Project Planner / Programmer working at group level, but mostly on Crossrail West M&E at the moment.

Experience Hours (Planning & Scheduling): 
550
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
0