%100- Poject Planning; Progress Reporting; CS Project

Advisor Planning - Sr Planning Engineer, Punj Lloyd Limited, (ALL EPC Projects) Sohar Refinery Methanol-Pipeline project

START Date: 
July, 2007
END Date: 
February, 2012

Project Planning & Scheduling, Invoicing, Client billing, PMS preparation and certification, Reporting Daily, weekly and monthly, Coordination for 780 Km Pipeline project, Micro planning for critical activities, Cost management, Presentation preparation, orgainizing meeting for progress review, client coorpondance etc.

Experience Hours (Planning & Scheduling): 
10300
Experience Hours (Cost Management): 
2050

Planning Manager, Birse Civils, London Underground Extended Arm Contract

START Date: 
October, 1998
END Date: 
April, 2001

Planning Manager

Setting up the planning system & procedures in accordance with NEC requirements;
Providing support to project teams;
Providing early warnings of conflicts and issues to the business manager;
Analysing contractor’s programmes;
Maintain 'as built' programmes incorporating variations;
Planning the design & build, civil, mechanical & electrical interfaces and assisting in developing the operational procedures for ISO accreditation.

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0