Planning & Billing Enginner, J KUMAR INFRAPORJECT LIMITED, Mumbai Metro

START Date: 
July, 2011
END Date: 
March, 2014
  J Kumar Infraprojects Limited Jul 2011-Mar 2014  Prepared and raised Monthly Running Account Bills to the Client and Consultant Prepared progress reports, planning & monitor site progress accordingly Geotechnical investigation Site execution of R.C.C & finishing works of Metro substructure Prepared Bar Bending Schedule for foundation and substructure Worked out resources (Manpower, Materials & Machinery) required for completion of tasks as per schedule
Experience Hours (Planning & Scheduling): 
5900
Experience Hours (Cost Management): 
2200