Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Pakistan (AS.PK)

Site Mechanical Engineer, Adnan Asdar And Associates, Construction of HVAC and Co-generation plant

START Date: 
May, 2004
END Date: 
October, 2004
RESPONSIBILITIES 1. Coordinating information for creating unique Program for individual Projects using MS Project 2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours. 3. Preparation of project Cash flow. 4. Preparation of man power Calculation & utilization schedule. 5. Updating progress of work using MS Project. 6. Preparation of recovery program to catch up delays 7. Preparation of short term detailed schedule based on baseline schedule. 8. Attending meeting with Client and Sub-Contractor for resolving issue on Weekly basis.

Site Mechanical Engineer, Adnan Asdar And Associates, Construction of HVAC and Co-generation plant

START Date: 
May, 2004
END Date: 
October, 2004
RESPONSIBILITIES 1. Coordinating information for creating unique Program for individual Projects using MS Project 2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours. 3. Preparation of project Cash flow. 4. Preparation of man power Calculation & utilization schedule. 5. Updating progress of work using MS Project. 6. Preparation of recovery program to catch up delays 7. Preparation of short term detailed schedule based on baseline schedule. 8. Attending meeting with Client and Sub-Contractor for resolving issue on Weekly basis.

Site Mechanical Engineer, Adnan Asdar And Associates, Construction of HVAC and Co-generation plant

START Date: 
May, 2004
END Date: 
October, 2004
RESPONSIBILITIES 1. Coordinating information for creating unique Program for individual Projects using MS Project 2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours. 3. Preparation of project Cash flow. 4. Preparation of man power Calculation & utilization schedule. 5. Updating progress of work using MS Project. 6. Preparation of recovery program to catch up delays 7. Preparation of short term detailed schedule based on baseline schedule. 8. Attending meeting with Client and Sub-Contractor for resolving issue on Weekly basis.

Site Mechanical Engineer, Adnan Asdar And Associates, Construction of HVAC and Co-generation plant

START Date: 
May, 2004
END Date: 
October, 2004
RESPONSIBILITIES 1. Coordinating information for creating unique Program for individual Projects using MS Project 2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours. 3. Preparation of project Cash flow. 4. Preparation of man power Calculation & utilization schedule. 5. Updating progress of work using MS Project. 6. Preparation of recovery program to catch up delays 7. Preparation of short term detailed schedule based on baseline schedule. 8. Attending meeting with Client and Sub-Contractor for resolving issue on Weekly basis.

Site Mechanical Engineer, Adnan Asdar And Associates, Construction of HVAC and Co-generation plant

START Date: 
May, 2004
END Date: 
October, 2004
RESPONSIBILITIES 1. Coordinating information for creating unique Program for individual Projects using MS Project 2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours. 3. Preparation of project Cash flow. 4. Preparation of man power Calculation & utilization schedule. 5. Updating progress of work using MS Project. 6. Preparation of recovery program to catch up delays 7. Preparation of short term detailed schedule based on baseline schedule. 8. Attending meeting with Client and Sub-Contractor for resolving issue on Weekly basis.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Market Place

No results found... (try selecting a different content filter)

Syndicate content