Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Project Planning Engineer, SEFEC Engineering Pvt Ltd, Construction of Pressure vessel, Heat Exchanger , Reactors etc

START Date: 
March, 2004
END Date: 
April, 2004

RESPONSIBILITIES

1. Coordinating information for creating unique Program for individual Projects using MS Project

2. Preparation of Project Budget & Calculation of detailed man-hours, machine hours.

3. Preparation of project Cash flow.

4. Preparation of man power Calculation & utilization schedule.

5. Updating progress of work using MS Project.

6. Preparation of recovery program to catch up delays

7. Preparation of short term detailed schedule based on baseline schedule.

8.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content