Saudi Arabia (AS.SA)

Area Planning Manager, BECHTEL, Riyadh Metro Project Line 1 &2

START Date: 
August, 2013
END Date: 
January, 2015
  • Working in the central Planning for the whole Line1 & Line 2 (38 stations, 5 park & ride, 7 bridges, tunnels, cut & cover, NATM tunnel)
  • Inform and Guide all Project Managers to deliver all project activities within time & budget
  • Liaise with internal and external customer stakeholders to identify and proactively manage changes to the Projects within the scope
  • Conduct Progress weekly meeting and workshops with Project managers to resolve critical issues pertaining to Design, Permits, Procurement, manpower, machinery and construction
  • Prepare
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

nile researsh institute Planner

START Date: 
March, 2005
Current Role

hany nabegh

First Name: 
hany
Last Name: 
nabegh
 am a civil engineer graduated in 2004 skilled in planning using primavera p6 where i can
1- Forming EPS.
2- Forming OBS.
3- FormingWBS and WBS milestones for the projects.
4- Entering activities + making logical relashionships based on experience.
5- Making activities steps.
6- Duration estimation for activities based of production rates + experience.
7- Calenders for projects.
8- resourses and roles dictionary.
9- Cost accounts + cost estimation.
10- loading resources on activities.
11- Resources leveling.
Professional Since: 
Oct-2008 (16.1 yrs experience)
Oldest experience: 
Mar 2005 (19.7 yrs experience, WARNING: 3.6 years variance with Professional Since)
Years Experience: 
0

Planning Manager, El Seif Engineering Contracting Co. - Riyadh, All 10+ corporate projects

START Date: 
March, 2005
END Date: 
January, 2014

Planning / Control Manager. Planning & Control for the construction of High Quality High-Rise Towers, Hotels, Hospitals & Infrastructure Works. Represent the Company's interests with relevant external parties & have significant impact & input on the planning / organizational issues & relevant decision making of the Project's Senior Management team.

Dar Al Handasah (Shair & Partners) Planner

START Date: 
February, 2005
Current Role

Hisham Hassan

First Name: 
Hisham
Last Name: 
Hassan
Professional Since: 
Nov-1986 (38.0 yrs experience)
Oldest experience: 
Feb 2005 (19.7 yrs experience, WARNING: 18.2 years variance with Professional Since)
Years Experience: 
0

Orascom Planner

START Date: 
February, 2005
Current Role

Yasser Barakat

First Name: 
Yasser
Last Name: 
Barakat
Professional Since: 
Nov-1993 (31.0 yrs experience)
Oldest experience: 
Feb 2005 (19.8 yrs experience, WARNING: 11.2 years variance with Professional Since)
Years Experience: 
0

START Date: 
February, 2005
Current Role

Shanmugam Thangamuthu

First Name: 
Shanmugam
Last Name: 
Thangamuthu
Professional Since: 
Aug-1993 (31.3 yrs experience)
Oldest experience: 
Feb 2005 (19.8 yrs experience, WARNING: 11.5 years variance with Professional Since)
Years Experience: 
0

Market Place

No results found... (try selecting a different content filter)

Syndicate content