Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Saudi Arabia (AS.SA)

Ramil Macawali

First Name: 
Ramil
Last Name: 
Macawali

Projects Management

Planner & Scheduler

AutoCAD Operator

Professional Since: 
May-1993 (31.8 yrs experience)
Oldest experience: 
May 1994 (30.8 yrs experience, WARNING: 1.0 years variance with Professional Since)
Years Experience: 
43

Construction Project Planner / Senior Planner, "Haif Construction Co.,Saudi arabia", 1) Infrastructure 2) Sewerage Treatment Plant 3) Bridge works 4)Building works

START Date: 
May, 1994

- Preparing Construction Schedule at Bid Submission Stage.

- Preparing Detailed  Implementation Schedule (After Contract award).

- Preparing CPA (Critical Path Analysis) & Baseline Schedules.

- Developing Manpower histogram & Other Progress Tracking, “S” curves.

- Reporting Delay & Claims.

- Dealing  with Scope changes/Variances.

Ausama Ali

First Name: 
Ausama
Last Name: 
Ali

Technical Skills:

·         MS Office 2003/07/10 and Adobe Photoshop,

·         Autodesk : AutoCAD CIVIL3D & AutoCAD & AutoCAD land

·         Computer maintenance ( Software & Hardware )

·         Design Profiles.

 Experiences:

Professional Since: 
May-2005 (19.8 yrs experience)
Oldest experience: 
Apr 2005 (19.9 yrs experience, WARNING: 0.1 years variance with Professional Since)
Years Experience: 
43

4D Assistant Planning Consultant, Dongho Korean Saudi Limited Company, 15A

START Date: 
April, 2005

 Experiences:

Two years (Amounts  Calculator & Supervision & Asbiult  drawing) in Syria.

One year (Amounts Calculator & Supervision & Asbiult  drawing). Project wadi almoroj  in Syria.

One year (Asbiult drawing & Supervision ) Project Alnoblaa in Syria

Tow years (projects of water) for City Khamis Mushit in Kingdom of Saudi Arabia(Amounts Calculator & Asbiult drawing) .

Adnan Maqsood

First Name: 
Adnan
Last Name: 
Maqsood
Professional Since: 
Jun-2008 (16.7 yrs experience)
Years Experience: 
0

PLANNING ENGINEER, CCC (Consolidated Contractors Company), Rabigh Olefins Petrochemicals Refinery

START Date: 
December, 2006
END Date: 
July, 2007

-involved in overall progress measurement of the Project
-process all the information received from site and issue the weekly report for physical progress
-summarize and split the quantity by area of activity and then update weekly the progress use Pyramid, an in house software provided by the company based by pyramid concept
- prepare the schedules for piping and mechanical discipline using the information received from all departments involved in this Project
-prepare the schedule 3 weeks look ahead for piping and mechanical discipline.

Experience Hours (Planning & Scheduling): 
1100
Experience Hours (Forensic Analysis): 
100

Bid/Project Planning Engineer, Kaefer C&D, DEVELOPMENT OF SIPCHEM PLANT JUBEL

START Date: 
October, 2008
END Date: 
December, 2009

 

ØEstablish and manage effectively a planning and progress control system in order to support the Project Manager decision making process and allow him to complete the project according to the internal baselines and in compliance with the contractual dates and requirements

ØEnsure any deviation from plan is promptly spotted and analyzed, final time impact is estimated and the effect of corrective actions taken is monitored.

Bid/Project Planning Engineer, Kaefer C&D, development of sipchem plant jubel

START Date: 
May, 2013

Rizwan Wahid Khan                 

pHONE ->91-9421704333,+7 771 845 86 25

 

E-MAIL:- rizwan_wardha@yahoo.com, rizwan.wardha@hotmail.com         

Project Manager, MoHE ,Samsung SDS, ERP

START Date: 
August, 2002
Ministry of Higher Education, Riyadh ,KSA PROJECT MANAGER - PMO November 2012 – Present Responsible for providing tactical management and administration / leadership support to project teams, ensuring that the projects proceeds within the agreed tolerances of time / budget, and deliver a fit-for-purpose outcome to the customer.· Managing IT projects and driving project teams from the start through to completion. · Coordinating multidisciplinary global project teams to deliver technology projects of varying size and complexity, focusing sp

Fadi Qaisi

First Name: 
Fadi
Last Name: 
Qaisi

 

FADI AL QAISI
PROJECT MANAGER

 

Key skills

 

AREAS OF EXPERTISE

Professional Since: 
Aug-2002 (22.5 yrs experience)
Oldest experience: 
Aug 2002 (22.5 yrs experience)
Years Experience: 
10

Market Place

No results found... (try selecting a different content filter)

Syndicate content