Construction Project Planner / Senior Planner, "Haif Construction Co.,Saudi arabia", 1) Infrastructure 2) Sewerage Treatment Plant 3) Bridge works 4)Building works

START Date: 
May, 1994

- Preparing Construction Schedule at Bid Submission Stage.

- Preparing Detailed  Implementation Schedule (After Contract award).

- Preparing CPA (Critical Path Analysis) & Baseline Schedules.

- Developing Manpower histogram & Other Progress Tracking, “S” curves.

- Reporting Delay & Claims.

- Dealing  with Scope changes/Variances.

- Maintain all contract related files and data bases in accordance with the Scheduling and Quality Manuals.

- Forecasting on an ongoing basis, prepare and communicate forecasts of each project’s projected volume  

  requirements in accordance with the Scheduling Manual and company quality procedures.

- Regular site visits and telephone conversations maintain a good rapport with site personnel and management. 

- Highlight potential problems in advance of supply.  Actively pursue programmes and critical information to maintain

  continuity of supply.