Italy (EU.IT)

Project Planner, Alstom Power, Coke Plant), Various Projects (Power Plants

START Date: 
October, 2011
END Date: 
December, 2012

development baseline schedule, definition critical paths, following updating and monthly reports, identification variances to planned performance

Sr. Project Planner, Saipem S.p.A., Gas Compression Stations Revamping

START Date: 
April, 2012

Sr. Project Planner at Saipem SpA for Gas Compression Stations Revamping for Snam Rete Gas and Stogit

MANUELA GIARDA

First Name: 
MANUELA
Last Name: 
GIARDA
Professional Since: 
Jan-2002 (22.7 yrs experience)
Oldest experience: 
Sep 2009 (15.0 yrs experience, WARNING: 7.7 years variance with Professional Since)
Years Experience: 
4

Project Planner, Corvallis S.p.A., Implementation of a Planning Model

START Date: 
May, 2013
Junior Planner. Project Planning and Controlling Activity, consulting for the implementation of Project Managementsystems. Followed Projects:
  • ABB S.p.A.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
300

calogero montana

First Name: 
calogero
Last Name: 
montana

concrete supervisor quality

Professional Since: 
Aug-1977 (47.1 yrs experience)
Years Experience: 
0

Planner and Cost Controller Junior, Filippo Fochi Energia, Various Power Gen Projects

START Date: 
April, 1993
END Date: 
July, 1995

Started work with Filippo Fochi Energia in Italy as a Junior Planner & Cost Controller; power generation, seeing my technical background from the Navy working with steam generators and steam/gas turbines it was a well suited start to my carreer.

These first experiences in the planning world were so good, it created very strong foundations for all the years to come to build upon. We were already doing earned value back then, don't think it's some new concept.

guido ross

First Name: 
guido
Last Name: 
ross
Oldest experience: 
Jun 1995 (29.2 yrs experience, WARNING: 25.4 years variance with Professional Since)
Years Experience: 
43

planner, ABB, 2000MW coal power plant

START Date: 
June, 1995

project planner from 1995, Scheduling and reporting for 2000MW coal power plant

marco pona

First Name: 
marco
Last Name: 
pona
Oldest experience: 
Jan 2008 (16.7 yrs experience, WARNING: 38.0 years variance with Professional Since)
Years Experience: 
0

project planner, bombardier transportation Italy, PMO

START Date: 
September, 2013

I'm PMI-PMP Certified

I'm supporting Project Manager in Planning and Progress Controll

I'm also involved in bid preparation and Risks and Opporunity Assesment