Western Route Export Pipeline Kura West River Crossing Replacement Project

Planning & Controls Engineer, "Tekfen Construction and Installation Co., Inc.", Western Route Export Pipeline Kura West River Crossing Replacement Project

START Date: 
September, 2007
END Date: 
February, 2008
  • Preparation of Construction Schedule (73000 man-hours)
  • Updating Construction Schedule.
  • Preparation of Daily, Weekly and Monthly Reports
  • Budget Preparation
  • Preparation of Payment Certificates
  • Preparation of Variation Orders
  • Control of Personnel Time Recording