Waste Water Treatment Plant & Reverse Osmosis Plant - Construction

Senior Planning Engineer, Concorde - Corodex Group, Supply, Construction, Installation & Commissioning of Waste Water Treatment Plant & Reverse Osmosis Plant

START Date: 
July, 2008
END Date: 
January, 2011
  • Prepared and submitted Baseline Programmes and S-Curves with Man Power & Equipment Histograms
  • Monitoring the Progress of the work as per the schedule
  • Prepared and presented the bar charts and variance reports to higher management during periodical progress meetings
  • Reviewing the project progress by highlighting the critical path and the critical activities to be performed by Construction department time to time for timely completion of the project.
  • Preparing Daily, Weekly & Monthly Progress Reports
  • Updating & follow-up wit