Washington Metro Area Transit Authority Orange Line Extension Claim

Claims Analyst, CT Summation Case Management Database, Senior Construction Consultant, TDF, LLC, Washington Metro Area Transit Authority Orange Line Extension Claim

START Date: 
April, 2007
END Date: 
October, 2007

Construction Consultant, P5 As-built scheduler for defense $30M litigation of $200M WMATA project; CT Summation software

§  25,000 activities scheduled from inspection dailies into as-built

§  Develop codes and filters, code activities 8 ways, global code changes for improved as-built analysis

§  Review business processes, spec and 300K image project record for claim analysis

§  First draft of report summarily ended claim, adjudication lower than owner’s initial offer

Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
500