- Preparation of fully resource and expense loaded Baseline Construction programme in Microsoft Project 2010 with 15000+ activities.
- Project management & cost control process, responsible for progress planning & monitoring.
- Prepared & presented monthly reports to top management in monthly project meetings.
- Prepared resource optimization report.
- Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
- Preparation of Delay tables, Productivit
Experience Hours (Planning & Scheduling):
2000
Experience Hours (Cost Management):
250
Experience Hours (Forensic Analysis):
250
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Posted Wed, 2012-08-15 10:07 by Gurmeet Walia
- Preparation of Detailed Project Budget at Pre Contract as well as Post Contract Stage considering each and every items of the BOQ.
- Preparation of Monthly Cash flow for various highway Projects.
- Preparation of Pre-qualification and Post-qualification Documents.
- Working of Quantities for BOT Projects.
- Preparation of Construction Programme at Pre Contract Stage.
- Reviewing & maintaining the status of Bank Guarantees regarding to the Contract.
- Preparation of Joint Venture Agreement, Co-ordination with Co./JV Partners, Corresp
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise:
Market Place
No results found... (try selecting a different content filter)
Website Development by Hunt Data Solutions and Vit-al Interactive. CMS:
Drupal THEME:
Acquia Marina