· Creation and linking of top-level and detail Project schedulers in Oracle Primavera 18 (detail scheduler based on “waves method”)
· Creation of Methodology of Schedule and Reporting (rules for planners of General Construction Contractor)
· Weekly Project controlling progress based on level 2 Schedule and report of General Contractor
· Organization and coordination weekly meetings with