UCH II Expansion Project (404 MW-Combined Cycle Power Plant)

Project Scheduler, URS Infrastructure & Environment UK Limited, UCH II Expansion Project (404 MW-Combined Cycle Power Plant)

START Date: 
February, 2012

 

I am involve in the following responsibility during this project

§  Monitor the project schedule on Primavera P6 and project progress against the EPC Contractor’s construction and commissioning schedule and assist the EPC Contractor’s planning and interfacing activities to limit the impact of any programme deviations.

§  Assist the Owner in all aspects of site supervision of EPC Contractors (Hyundai and Descon)