TOTAL OML 99

PROJECT CONTROLS ENGINEER, Fluor- Cnc , CHEVRON DIBI LONG, NAVGAS GAS PLANT, EXXON MOBIL INIM, TOTAL OML 99, TOTAL OML 100 ETC

START Date: 
March, 2004
END Date: 
August, 2011
  • Prepared a level 4 CPM schedule plus a comprehensive Basis of schedule document
  • Preparing level 4 Progress Measurement Matrix to calculate earned values Linked to the MDR
  • Reviewed Subcontractors calculation & schedule
  • Monitored weekly trends; SPI(t), CPI and to advise the project manager
  • Prepared weekly & Monthly report
  • Gave Project Controls advise as needed
  • Participated in weekly meetings with client
  • Re-forecasting planned Project Progress
  • Monitoring and controlling all contractors on the Project
  • Preparati

PROJECT CONTROLS ENGINEER, Fluor- Cnc , CHEVRON DIBI LONG, NAVGAS GAS PLANT, EXXON MOBIL INIM, TOTAL OML 99, TOTAL OML 100 ETC

START Date: 
March, 2004
END Date: 
August, 2011
  • Prepared a level 4 CPM schedule plus a comprehensive Basis of schedule document
  • Preparing level 4 Progress Measurement Matrix to calculate earned values Linked to the MDR
  • Reviewed Subcontractors calculation & schedule
  • Monitored weekly trends; SPI(t), CPI and to advise the project manager
  • Prepared weekly & Monthly report
  • Gave Project Controls advise as needed
  • Participated in weekly meetings with client
  • Re-forecasting planned Project Progress
  • Monitoring and controlling all contractors on the Project
  • Preparati