TIME Telekom Project

Project Planner, TIME Plessey Telecommunications S/B, TIME Telekom Project

START Date: 
September, 1995
END Date: 
January, 1997
  • Develop a detailed schedule for the TIME Telekom Network Construction covering laying the duct, fibre optic cables along Peninsular Malaysia (3,600 km), laying submarine fibre optic cables (1,624 km), cabins installation and rooms
  • Monitor daily and weekly progress on all duct constructions, fiber optics laying including way leaves and permits
  • Produce and report the monthly progress status to General Manager
  • Provide analysis on the existing LAN and document all workstations and servers specifications
  • Propose and implement new Network Communication Infrast