Polypropolene Plant 2 (PP2)

Scheduling Engineer, Technip France, Polypropolene Plant 2 (PP2)

START Date: 
October, 2005
END Date: 
May, 2006

I was part of a core team of individuals that was site based. The project was multi disciplinary, design, procurement, fabrication and erection of piping, civil works, structural steel fabrication and erection, electrical and instrumentation erection, in the petrochemical industry. Using Primavera software, I helped to compile & update level 4 integrated schedules, providing weekly, as well as monthly reports for Management meetings. All subcontractors’ schedules were incorporated as sub-projects into our over-all schedule, creating a level 4 integrated schedule.