- Schedule development and monitoring periodically :L1/ L2/ L3 schedules project for concept, FEED and Detailed Engineering, procurement phase of project by defining WBS, activities & their codes.
- Monitoring deliverables for FEED & detailed engineering stages.
- Tracking actual man-hours against the budgeted man-hours.
- Bid evaluation of vendors & consultants with respect to project planning & control requirements.
- Generating S-Curves as per the progress for MIS Reporting.
- Preparation of Planning Package with all