Jubail Industrial City

Specialist Project Controls, BECHTEL, Jubail Industrial City

START Date: 
April, 2007
END Date: 
September, 2007

Expert Project Controls, establishment of Integrated Project controls system for Jubail Industrial City , Royal Commission.

Project Controls Engineering - cost and planning, BECHTEL, Jubail Industrial City

START Date: 
July, 2007
Develops and monitors short term (14 weeks) preliminary construction schedules.Determines critical-path activities, reviews schedule data, methods for activity durations, time extension and constraints to establish logical work sequences for assigned discipline or specialties. Monitors schedule deviation for assigned disciplines or specialties including subcontractor submittals, and recommends corrective action/workaround solutions for project considerations.

Project Controls Engineering - cost and planning, BECHTEL, Jubail Industrial City

START Date: 
July, 2007
END Date: 
January, 2014

Develops and monitors short term (14 weeks) preliminary construction schedules.
-Determines critical-path activities, reviews schedule data, methods for activity durations, time
extension and constraints to establish logical work sequences for assigned discipline or specialties.
-Monitors schedule deviation for assigned disciplines or specialties including subcontractor
submittals, and recommends corrective action/workaround solutions for project considerations.
-Prepares, develops, & updates Contractors Construction Schedule (P6.7 & P3), Bi-weekly &
Executive

Cost and Planning/Scheduler Engineer, Bechtel Corporation, Jubail Industrial City

START Date: 
July, 2007

Experience : July 26, 2007 to Present-Planning/Scheduler & Cost Engineer
BECHTEL Corporation, Jubail City, Kingdom of Saudi Arabia
Project: JUBAIL INDUSTRIAL CITY (~US$ 875 Million Annual Budget)
-Develops and monitors short term (14 weeks) preliminary construction schedules.
-Determines critical-path activities, reviews schedule data, methods for activity durations, time
extension and constraints to establish logical work sequences for assigned discipline or specialties.
-Monitors schedule deviation for assigned disciplines or specialties including subcontractor
su