Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Hunter Treatment Alliance

Project Scheduler, CH2M Hill, Hunter Treatment Alliance

START Date: 
November, 2009

I am employed by CH2MHILL as the Project Scheduler on the Hunter Treatment Alliance in Newcastle which is a $240 million five-year program of work with the Hunter Water Corporatation.

We have now completed all four Stage 1 Waste Water Treatment Plants successfully and on time, and are nearing completion of Stage 2 as of January 2012.

I am responsible for developing all project schedules and making sure that correct scope of work is reflected in all schedules.