Expansion of 33kv Network in Al Alin Region

Planning Engineer, Larsen and Toubro, Expansion of 33kv Network in Al Alin Region

START Date: 
September, 2011
END Date: 
September, 2013

ü  Scheduling for EPC Construction of substation and distribution system  with Primavera 6-8.1

 

ü  Resource loading of schedule & Manpower histogram

 

ü  Project Trend Analysis using S curve

 

ü  Critical path Analysis

 

Planning Engineer, Larsen & Toubro Construction, Expansion of 33kv Network in Al Alin Region

START Date: 
September, 2011
END Date: 
September, 2013

EPC Planning for Substaion projects and scheduling, costing, Subcontractor Finalization, Client Billing 

Planning Engineer, Larsen & Toubro Construction, Expansion of 33kv Network in Al Alin Region

START Date: 
September, 2011
END Date: 
September, 2013

EPC Planning for Substaion projects 

MIS Reports , Scheduling , costing, 