Excution of Gas Compression and Reinjection Station

Assistant Planning Engineer, Bentini S.p.A, Excution of Gas Compression and Reinjection Station

START Date: 
March, 2016
END Date: 
August, 2017
Responsibilities :Preparing master and baseline schedule and updating work schedule That including resources of Cost, labor Controlling daily, weekly and monthly planning reportsPreparing planning reports for meeting with client and upper ManagementAnalysis of unit prices, material consumptions, actual unit man‐hours Cost control and project budget planning