As the focal point for all project services on the EPC contract on the Draugen Asset, it was my responsibility to ensure that every project had the correct level of project controls applied on that project.  This meant coordinating all call-offs, especially specifying the deliverables and level of detail that were to be provided.  I had to ensure that the project met the PCAP (Project Controls Assurance Process) requirements and  to sign off the applicable Decision Gate.  This involved establishing the applicable estimate and schedule prior to commencement of phase, ensu

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
50