Devenick & Andrew Area Development

Lead Planning Engineer, BP, Devenick & Andrew Area Development

START Date: 
July, 2010
END Date: 
December, 2011

Responsible for the planning internally and externally on two major projects (BP Andrew and Devenick) with a combined value of over £1bn.

Project Controls Team Lead, BP, Devenick & Andrew Area Development

START Date: 
July, 2009
END Date: 
June, 2010

Responsible for planning and cost control internally and externally on two major projects BP Andrew and Devenick.

Senior Planning Engineer, BP, Devenick & Andrew Area Development

START Date: 
July, 2008
END Date: 
June, 2009

Responsible for the generation of Greenfield and Brownfield Master Control Schedules for Category 2 Projects.