Managing and leading the Planning Team on the Muscat International and Salalah Airport Project

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
250

Planning Manager, Turner & Townsend, Development of Muscat & Salalah Airports, OMAN

START Date: 
March, 2013
END Date: 
June, 2013

Management of the Planning Team for Ultra-Ithra contractors for MC6 Master Systems Integrator for Airport IT Systems, IT Networks & Security Systems.

Experience Hours (Planning & Scheduling): 
500

Area Planner, COWI-Larsen JV, Development of Muscat & Salalah Airports

START Date: 
July, 2008
  • Preparation of Master Programme
  • Establishment of Contract Milestones
  • Preparation of Employer’s Requirement document
  • Management of time planning related to MC1 Contract
  • Review of Contractor’s Contract Programme
  • Review of Contractor Weekly and Monthly reports
  • Maintaining time related records
  • Responding to Contractor’s time related contractual correspondence
  • Assessment of time impacts for any variation to the works
  • Conducting regular progress meetings with the Contractor
  • Review Contractor