Construction of MX-01 & MX-04 Towers

PLANNING ENGINEER, Eaaastern International, Construction of MX-01 & MX-04 Towers

START Date: 
August, 2012

o   Create Cost and Resource loaded Baseline as per FIDIC contract clauses and got approval from consultant/Client.

o   Preparation of upto level 6 schedule for different contract requirements including Tender, Recovery and Acceleration Schedules.

o   Coordinate and guide project execution team to successful timely completion of project. Closely monitoring the project schedule and progress, and provide reports as required to execute the project as per contract.

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
3000